Question

1 Approved Answer

b . Suppose direct costs of crashing the project only increased $ 5 , 0 0 0 per day crashed at a steady rate (

b. Suppose direct costs of crashing the project only increased $5,000 per day crashed at a steady rate (starting with $125,000 on day 60). How many days would you advise that the project be crashed? Show your work. Project Duration (Days) Direct Costs Overhead Costs Penalty Charges Total Cost
60 $125,000 $15,500 $50,000 $190,500
57 $140,000 $13,000 $35,000 $188,000
54 $175,000 $10,500 $20,000 $205,500
51 $210,000 $8,000 $5,000 $223,000

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Understanding And Managing Public Organizations

Authors: Hal G. Rainey, Sergio Fernandez, Deanna Malatesta

6th Edition

1119705894, 978-1119705895

More Books

Students also viewed these General Management questions

Question

assess the infl uence of national culture on the workplace

Answered: 1 week ago