(b) The development of a 36 storey commercial building is in progress and the total construction period for this project is 22 months. Basement area will take up 4 months to construct and typical floor construction will be 3 floors/month. The last 3 months will be for relevant authority inspection and Test & Commissioning (T&C) to obtain TOP/CSC, whereby Projected Progress and Payment to the contractors had been estimated by the Project Manager and incorporated onto the Master Schedule. Progress of work is presently at the 8th month but delay had occurred for the basement works owing to machine breakdowns. Furthermore, with labour shortage contractor could not fulfil their targeted productivity. Analyze the situation and propose appropriate instructions and/or directions to the contractor in order to catch up the schedule to obtain successful completion. The instruction and/or directions must cover Contractual, Financial and Implementation aspects. You may draw and/or write necessary information onto Figure 3 (and attach to your answer book) to show the strategy of how to complete. Max: 15 marks (b) The development of a 36 storey commercial building is in progress and the total construction period for this project is 22 months. Basement area will take up 4 months to construct and typical floor construction will be 3 floors/month. The last 3 months will be for relevant authority inspection and Test & Commissioning (T&C) to obtain TOP/CSC, whereby Projected Progress and Payment to the contractors had been estimated by the Project Manager and incorporated onto the Master Schedule. Progress of work is presently at the 8th month but delay had occurred for the basement works owing to machine breakdowns. Furthermore, with labour shortage contractor could not fulfil their targeted productivity. Analyze the situation and propose appropriate instructions and/or directions to the contractor in order to catch up the schedule to obtain successful completion. The instruction and/or directions must cover Contractual, Financial and Implementation aspects. You may draw and/or write necessary information onto Figure 3 (and attach to your answer book) to show the strategy of how to complete. Max: 15 marks