B The Finance and Accounting Departments of your company remind you a rule exists that states that every item whether a material or a finished good must be counted at least twice per year. The reason you are conducting the ABC analysis is the plant has an issue with running out of material and either making a mid shift unplanned changeover or loses the last 15 to 90 minutes of a shift as the changeover cannot be accomplished in a manner that makes it worthwhile to hold the crew. Estimates are that up to 2.5% of run time is lost to short shifts and unplanned changes. Studies suggest than 1% could be eliminated with a robust cycle count program, Approximately 1% is related to changeovers that cannot be avoided and S% is related to supplier issues. You are permitted to recommend the cycle count program that just meets the company requirements (which is already partially in place) and you will get 20% on this problem as long as you calculate the amount of time spent on counting correctly. You also will not reduce downtime by 1% but will only save.25% w wa Www * THE ht 11 H 400 H son 2001 WY W IL 1 DES GAL 1 101 LE 21 VE DOT 11 1 PUR WE 1 $ IP IVE WE LO 1 11 www. und w LE 1 10 1 5 20 HOR 1 14 he S tur M W OT SCHE 30 1. Materials and packaging Instructions Accycle count B The Finance and Accounting Departments of your company remind you a rule exists that states that every item whether a material or a finished good must be counted at least twice per year. The reason you are conducting the ABC analysis is the plant has an issue with running out of material and either making a mid shift unplanned changeover or loses the last 15 to 90 minutes of a shift as the changeover cannot be accomplished in a manner that makes it worthwhile to hold the crew. Estimates are that up to 2.5% of run time is lost to short shifts and unplanned changes. Studies suggest than 1% could be eliminated with a robust cycle count program, Approximately 1% is related to changeovers that cannot be avoided and S% is related to supplier issues. You are permitted to recommend the cycle count program that just meets the company requirements (which is already partially in place) and you will get 20% on this problem as long as you calculate the amount of time spent on counting correctly. You also will not reduce downtime by 1% but will only save.25% w wa Www * THE ht 11 H 400 H son 2001 WY W IL 1 DES GAL 1 101 LE 21 VE DOT 11 1 PUR WE 1 $ IP IVE WE LO 1 11 www. und w LE 1 10 1 5 20 HOR 1 14 he S tur M W OT SCHE 30 1. Materials and packaging Instructions Accycle count