B1. Use the following information in the activities table of an information technology project for XYZ Hospital and draw a Gantt chart for the project.
B1. Use the following information in the activities table of an information technology project for XYZ Hospital and draw a Gantt chart for the project. Activity Dependencies Duration Activity /Predecessors (days) A 3 B A 4 A 2 D B 1 E B, C 3 F DE 4