Barani Institute of management sciences initiates an IT project Students Portal and assigns its development task to the ESS software house on September 01, 2020.

Barani Institute of management sciences initiates an IT project Students Portal and assigns its development task to the ESS software house on September 01, 2020. Choose the project planned value of your choice between 250000 and 300000, earned value after 6 month between 200000 and 230000, Actual Cost between 300000 and 330000, Budget at Completion 5000000. It was started on September 01, 2020 and March 20, 2021 was declared as its tentative completion date. Answer the following questions.

  1. Compute the Cost variance, Schedule variance, Cost performance Index, Schedule Performance Index and EAC.
  2. Project will be under budget or over budget

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Fundamentals Of Database Systems

Authors: Sham Navathe,Ramez Elmasri

5th Edition

B01FGJTE0Q, 978-0805317558

More Books

Students also viewed these Databases questions

Question

5-6 How will MIS help my career?

Answered: 1 week ago