Question

1 Approved Answer

Barriers Constructions Ltd were contracted to build artificial reefs by October 31 st in order to break the strong currents and waves that often damage

Barriers Constructions Ltd were contracted to build artificial reefs by October 31st in order to break the strong currents and waves that often damage the seawall along the coastal area of Utopia City. In the second week, of September there is an earthquake just a kilometre from their worksite.  They have been advised that they will have to stop work indefinitely. The project is delayed but Utopia City still wants to charge a penalty for $200 a day over the deadline of the project. 



Has the contract been discharged by frustration? Give reasons and state a case to support your answer.?

Step by Step Solution

3.48 Rating (151 Votes )

There are 3 Steps involved in it

Step: 1

The situation described suggests that the contract between Barriers Constructions Ltd and Utopia City may have been discharged by frustration Frustrat... blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Cost Accounting A Managerial Emphasis

Authors: Charles T. Horngren, Srikant M. Datar, Madhav V. Rajan

15th edition

978-0133428858, 133428850, 133428702, 978-0133428704

More Books

Students also viewed these Accounting questions

Question

I want simple use case and Activity diagram for Train booking app

Answered: 1 week ago

Question

Identify six common problems with goal setting.

Answered: 1 week ago

Question

explain the main theories of concentration effects,

Answered: 1 week ago

Question

discuss the sources of sport confidence,

Answered: 1 week ago