Based on the following crash cost table, what would be the minimum time to complete the project described below whose normal costs are shown in

  1. Based on the following crash cost table, what would be the minimum time to complete the project described below whose normal costs are shown in the table below. What would be the added cost to complete the project within this minimum time?

Normal

Normal

Crash

Crash

Cost per week

Activities

Nodes

Weeks

$

Weeks

$

$

A

(1,2)

4

$4,000

2

$6,000

$1,000

B

(1,3)

2

$1,200

1

$2,500

$1,300

C

(1,4)

3

$3,600

2

$4,800

$1,200

D

(2,5)

1

$1,000

0.5

$1,800

$1,600

E

(3,5)

5

$6,000

3

$8,000

$1,000

F

(4,6)

4

$3,200

3

$5,000

$1,800

G

(5,7)

3

$3,000

2

$5,000

$2,000

H

(3,6)

0

0

0

0

-

I

(6,7)

6

$7,200

4

$8,400

$600

J

(7,8)

2

$1,600

1

$2,000

$400

K

(8,9)

5

$3,000

3

$4,000

$500

L

(8,10)

3

$3,000

2

$4,000

$1,000

M

(9,10)

4

$1,600

3

$2,000

$400

N

(10,11)

1

$700

1

$700

-

O

(9,12)

4

$4,400

2

$6,000

$800

P

(11,12)

2

$1,600

1

$2,400

$800

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Handbook Of Communication Audits For Organisations

Authors: Owen D.W. Hargie, Dennis Tourish

1st Edition

0415186420, 978-0415186421

More Books

Students also viewed these Accounting questions

Question

Describe the linkages between HRM and strategy formulation. page 74

Answered: 1 week ago

Question

Identify approaches to improving retention rates.

Answered: 1 week ago