Based on the following table, calculate the ES, EF, LS, LF times and the slack for activity E. Activity Time Immediate Predecessor A 3 -
Based on the following table, calculate the ES, EF, LS, LF times and the slack for activity E.
Activity Time Immediate Predecessor
A 3 -
B 3-
C 4A
D 5 A
E 6 B
F 7 C,D,E
A. | ES = 0, EF = 3, LS = 1, LF = 4, slack = 1 | |
B. | ES = 3, EF = 9, LS = 3, LF = 9, slack = 0 | |
C. | ES = 0, EF = 3, LS = 0, LF = 3, salck = 0 | |
D. | ES = 3, EF = 7, LS = 5, LF = 9, slack 2 |