Based on the following table, calculate the ES, EF, LS, LF times and the slack for activity E. Activity Time Immediate Predecessor A 3 -

Based on the following table, calculate the ES, EF, LS, LF times and the slack for activity E.

Activity Time Immediate Predecessor

A 3 -

B 3-

C 4A

D 5 A

E 6 B

F 7 C,D,E

A.

ES = 0, EF = 3, LS = 1, LF = 4, slack = 1

B.

ES = 3, EF = 9, LS = 3, LF = 9, slack = 0

C.

ES = 0, EF = 3, LS = 0, LF = 3, salck = 0

D.

ES = 3, EF = 7, LS = 5, LF = 9, slack 2

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Product Marketing Management

Authors: Suat Ozsoy

1st Edition

9798481471693

More Books

Students also viewed these General Management questions

Question

Who responds to your customers complaint letters?

Answered: 1 week ago

Question

Under what circumstances do your customers write complaint letters?

Answered: 1 week ago