Question

1 Approved Answer

Based on the following table, how would you interpret the project performance? Fill in the second table, specifying the formula, result, and meaning. A B

Based on the following table, how would you interpret the project performance? Fill in the second table, specifying the formula, result, and meaning.

A

B

C

D

Budgeted

60,000

120,000

50,000

60,000

Planned

80%

65%

40%

30%

Performed

88%

50%

50%

5%

Actual Costs

55,000

80,000

30,000

30,000

Metric

Formula

Result

Meaning

BAC

-

EV

% performed x budget

PV

% planned x budget

AC

Non applicable

CV

EV AC

SV

EV PV

CPI

EV / AC

SPI

EV / PV

EAC

BAC / CPI

VAC

BAC - EAC

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Corporate Audit Scams A Threat To Corporate Governance

Authors: Sachi Kheskani

1st Edition

3659490148, 978-3659490149

More Books

Students also viewed these Accounting questions