Based on the information provided for a one-year project, answer the following questions. PV =$100,000 AC =$60,000 BAC=$125,000 ETC = $100,000 If 75% of the

Based on the information provided for a one-year project, answer the following questions.

PV =$100,000 AC =$60,000 BAC=$125,000 ETC = $100,000

  1. If 75% of the Planned Value was completed to date, what is the Earned Value of the work completed (round to nearest whole number)?

  1. What is the Cost Variance (round to nearest whole number)?

  1. What is the Schedule Variance (round to nearest whole number)?

  1. What is the Cost Performance Index (round to 2 decimals)?

  1. What is the Schedule Performance Index (round to 2 decimals)?

  1. How is the project progressing in terms of schedule (ahead, behind or on-schedule) and budget (under, over or on-budget)?

  1. If spending remains the same as the current rate to date, what is the Estimate at Completion for this project (round to nearest whole number)?

  1. If spending varies from current rate to date, what is the Estimate at Completion for this project (round to nearest whole number)?

  1. If spending remains the same as the current rate to date, what is the Variance at Completion (round to nearest whole number)?

  1. What is the % of the Project Complete (round to nearest whole %)?

  1. What is the % of budget spent (round to nearest whole %)?

  1. What is the To-Complete Performance Index required to achieve the original budget plan (round to 2 decimals)?
  2. Is the To-Complete Performance Index required to achieve the original budget plan harder, easier or the same as the efficiency performance to date?

  1. What is the To-Complete Performance Index required to achieve the revised budget plan if spending is the same as the current rate to date (round to 2 decimals)?

  1. Is the To-Complete Performance Index required to achieve the revised budget plan harder, easier or the same as the efficiency performance to date?

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Investing In Cryptocurrency For Dummies

Authors: Kiana Danial

1st Edition

1394200838, 978-1394200832

More Books

Students also viewed these Finance questions