Question
Based on the readings and Learning Module: Network Diagram and Critical path, build a network diagram for the project below and answer the questions. Consider
Based on the readings and Learning Module: Network Diagram and Critical path, build a network diagram for the "project" below and answer the questions. Consider the table below as a small project with the letters that represent actual named tasks (A-K) and all durations are in days. You will get an understanding of a predecessor and how this project is going to flow. What tasks can be completed at the same time and how others cannot start until another task is completed. There are times that multiple tasks need to be completed before another one can start.
QUESTIONS: (of the following questions after you have completed the network diagram)
- List out each path with total (in days). (i.e., A - B - C - D = 10 days).
- What is the critical path for this project and how long is it? Again, show as above.
- When is the earliest possible time that this project can be completed? State in days.
The chart to use: Task ID 1 23456 7 9 10 11 Task Name A B CD C E F G H I J K Duration 2 days 2 days 3 days 4 days 2 days 3 days 6 days 2 days 5 days 1 day 2 days Predecessors First task will not have a predecessor 1-A 1-A 1-A 2-B 3-C 4-D 5,6 --E, F 7,8 -- G, H 9 -- 1 8,10 -- H, J
Step by Step Solution
3.46 Rating (149 Votes )
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started