Question

1 Approved Answer

BC Electronics has begun a project consisting of activities A , . . . , G . The following table reports, for each activity, the

BC Electronics has begun a project consisting of activities A,..., G. The following table reports, for each activity, the normal time for activity completion, the crash time for activity completion, the normal cost for activity completion, the crash cost for activity completion, and the immediate predecessors.
Activity Time (in Weeks) Cost Immediate Predessors
Normal Crash Normal Crash
A 32 $1100 $1190 NA
B 21 $750 $850 NA
C 11 $650 $650 NA
D 75 $900 $1220 A
E 63 $1050 $1560 B
F 21 $1150 $1210 C
G 42 $1500 $1680 D, E
The minimum project completion time has been computed with the calculations of earliest start, earliest finish, latest start and latest finish for each activity with normal activity times for each activity on the project network copied below:
What is the project completion time for completing this project with each activity taking the normal time.
14
14
What is the total cost required for completing this project with each activity taking the normal time.
7100
7100(Enter only the amount, no $ sign, no comma.)
What is the incremental cost to reduce project activity completion for activity G?
90
90(Enter only the amount, no $ sign.)
What is the additional cost to reduce project completion time by one week?
90
90(Enter only the amount, no $ sign.)
What is the additional cost to reduce project completion time by 5 weeks?
590
690(Enter only the amount, no $ sign.)

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Business and Administrative Communication

Authors: Kitty o. locker, Donna s. kienzler

10th edition

77830105, 978-0077830106, 978-0073403182

More Books

Students also viewed these General Management questions

Question

7 . Mention three functions of Equipment categorization

Answered: 1 week ago