Beavis Construction Company was the low bidder on a construction project to build an earthen dam for $ 1 , 7 2 0 , 0

Beavis Construction Company was the low bidder on a construction project to build an earthen dam for $1,720,000. The project was begun in 2023 and completed in 2024. Cost and other data are presented below:
20232024
Costs incurred during the year $ 411,000 $ 1,020,000
Estimated costs to complete 959,0000
Billings during the year 465,0001,255,000
Cash collections during the year 365,0001,355,000
Assume that Beavis recognizes revenue upon completion of the project.
Required:
Prepare all journal entries to record costs, billings, collections, and profit recognition.
1. Record the entry for costs incurred during the year 2023.
2. Record the entry for billings during the year 2023.
3. Record the entry for cash collection during the year 2023.
4. Record the entry for revenue from long-term contracts.
5. Record the entry for costs incurred during the year 2024.
6. Record the entry for billings during the year 2024.
7. Record the entry for cash collection during the year 2024.
8. Record the entry for revenue from long-term contracts.
9. Record the entry to close the construction accounts.
image text in transcribed

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

How To Audit Anything The Pink Book Of Auditing Any Process

Authors: R. Alakbarov

1st Edition

1520195575, 978-1520195575

More Books

Students also viewed these Accounting questions