Question
Beavis Construction Company was the low bidder on a construction project to build an earthen dam for $1,760,000. The project was begun in 2020 and
Beavis Construction Company was the low bidder on a construction project to build an earthen dam for $1,760,000. The project was begun in 2020 and completed in 2021. Cost and other data are presented below:
2020 | 2021 | |
Costs incurred during the year | $399,000 | $1,060,000 |
Estimated costs to complete | 931,000 | 0 |
Billings during the year | 485,000 | 1,275,000 |
Cash collections during the year | 385,000 | 1,375,000 |
Assume that Beavis recognizes revenue on this contract over time according to the percentage of completion.
Required:
Prepare all journal entries to record costs, billings, collections, and profit recognition. (If no entry is required for a transaction/event, select "No journal entry required" in the first account field.)
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started