Question
Because both projects are the same size you can just calculate each projects MIRR and choose the project with the higher MIRR. (Remember, MIRR gives
Because both projects are the same size you can just calculate each projects MIRR and choose the project with the higher MIRR. (Remember, MIRR gives conflicting results from NPV when there are scale differences between the projects.)
12% |
Project X: 0 1 2 3 4
| | | | |
-5,000 1,000 1,500 2,000 4,000.00
2,240.00
1,881.60
1,404.93
9,526.53
5,000 17.49% = MIRRX
$5,000 = $9,529/(1 + MIRRX)4.
12% |
Project Y: 0 1 2 3 4
| | | | |
-5,000 4,500 1,500 1,000 500.00
1,120.00
1,881.60
6,322.18
9,823.78
5,000 18.39% = MIRRY
$1,000 = $1,636.37/(1 + MIRRY)4.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started