Question

1 Approved Answer

Because both projects are the same size you can just calculate each projects MIRR and choose the project with the higher MIRR. (Remember, MIRR gives

Because both projects are the same size you can just calculate each projects MIRR and choose the project with the higher MIRR. (Remember, MIRR gives conflicting results from NPV when there are scale differences between the projects.)

12%

Project X: 0 1 2 3 4

| | | | |

-5,000 1,000 1,500 2,000 4,000.00

2,240.00

1,881.60

1,404.93

9,526.53

5,000 17.49% = MIRRX

$5,000 = $9,529/(1 + MIRRX)4.

12%

Project Y: 0 1 2 3 4

| | | | |

-5,000 4,500 1,500 1,000 500.00

1,120.00

1,881.60

6,322.18

9,823.78

5,000 18.39% = MIRRY

$1,000 = $1,636.37/(1 + MIRRY)4.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Introduction To Estimating Economic Models

Authors: Atsushi Maki

1st Edition

0415589878, 978-0415589871

More Books

Students also viewed these Finance questions

Question

What do you need to know about motivation to solve these problems?

Answered: 1 week ago

Question

What is Larmors formula? Explain with a suitable example.

Answered: 1 week ago

Question

5. Identify three characteristics of the dialectical approach.

Answered: 1 week ago

Question

6. Explain the strengths of a dialectical approach.

Answered: 1 week ago

Question

4. Explain the strengths and weaknesses of each approach.

Answered: 1 week ago