Question

1 Approved Answer

Nellie is looking to upgrade and expand the research and testing area. The following information has been gathered and provided to Nellie. Activity Immediate predecessors

Nellie is looking to upgrade and expand the research and testing area. The following information has been gathered and provided to Nellie.

Activity

Immediate predecessors

Optimistic time (weeks)

Most likely time (weeks)

Pessimistic time(weeks)

Normal Cost ($)

Crash cost ($)

A

4

6

8

13,500

31,200

B

8

12

16

27,000

62,400

C

4

10

16

27,000

62,400

D

A

6

8

10

27,000

46,800

E

B

12

14

16

27,000

46,800

F

C

8

14

20

27,000

78,000

G

A

2

10

18

54,000

124,800

H

B

4

10

16

27,000

78,000

I

C

6

10

14

40,500

62,400

J

D, G

4

4

4

6,750

7,800

K

E, H

8

8

8

6,750

7,800

L

F

6

6

6

6,750

7,800


Required:

  1. Using an appropriate computer drawing program, draw the PERT network diagram for the project showing the task letters on the activity paths.
  2. Identify all the possible pathways and determine the critical path. 
  3. Determine the probability that the expansion will be completed in 30 weeks
  4. Nellie is prepared to pay an additional bonus of $15,000 per day if the project is completed in 28 days. Taking into consideration the costs involved in crashing the project, should the project be reduced to 28 days to receive the bonus (show workings)
  5. Using current literature (newspaper articles, academic journals etc), discuss some of the resource constraints that would make this upgrade and expansion challenging. Present these findings in a one-page cover letter addressed to Nellie. 

Step by Step Solution

3.44 Rating (157 Votes )

There are 3 Steps involved in it

Step: 1

PERT Network Diagram The PERT network diagram for Nellies project is shown below The task letters are marked on the activity paths The critical path is highlighted in red Critical Path ABEHK Possible ... blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Operations management processes and supply chain

Authors: Lee J Krajewski, Larry P Ritzman, Manoj K Malhotra

9th edition

9788131728840, 136065767, 8131728846, 978-0136065760

More Books

Students also viewed these Accounting questions