The accounting department at Northeast University is offering a combined five-year B.S./M.S. in accounting. The senior accounting

Question:

The accounting department at Northeast University is offering a combined five-year B.S./M.S. in accounting. The senior accounting professor has identified the project activities and any precedence relationships, as shown in Table 16-15. Three time estimates for each activity are included.
(a) Develop a network diagram for this project using AON notation.
(b) Calculate the expected time for each of the project activities.
(c) Identify the critical path for the project.
(d) Calculate the expected project completiontime.