Before calculating the process capability indices Cp and Cpk: Group of answer choices the customer requirements should be verified. the process stability should be evaluated
Before calculating the process capability indices Cp and Cpk:
Group of answer choices
the customer requirements should be verified.
the process stability should be evaluated on a control chart.
the process distribution should be evaluated.
all of the above.