below is earned value analysiscalvulation..kindly give answers with calculation
Rrolect Planning Data Your pro ect consists of the following actlvitles and it Is planned as follows: In addition: - Labour cost Activitues A, B, and C s90ihrs. For the remaining activites \$100ihr. - An audit meeting is required to at the end of week 6 at an estimated cost of $10,000 Actual Project Performance and the end of week 6- - Activities A. B, and audit meeling are completed. - Activities C, E and G are seventy five, fifty, and twenty five percent completed respectively. - Tho totai amounl spent up to this point is $115,000. Calculations from the start to the end of week. 6 : 1. Budiget at complelion 5 MARKS 2 Planned value S MARKS. 3. Eamed value 5 MAFKS. 4. CPI (lour decimal poinlS) AND INTERPRET THERESULT 2 MARKE 5. SPI (lour decimal ponts) ANU INTERPRET THERESULT. 2 MAESS MARKS) 7 From the end of waeke, how maid wore do you oraect to spard to anish the propect (2 MARKS) MARKS\} SHOW YOUR CALCULATONS NO calcuamons nomalk: You Gan wse the HTML Eolitor to enier xom anskgn Rfn fublexil You can also insed Your project consists of the following activities and it is planned as follows: In addition: - Labour cost: Activities A, B, and C $90/hrs. For the remaining activities $100/hr. - An audit meeting is required to at the end of week 6 at an estimated cost of $10,000. Actual Project Performance and the end of week 6: - Activities A, B, and audit meeting are completed. - Activities C, E and G are seventy five, fifty, and twenty five percent completed respectively. - The total amount spent up to this point is $115,000. Calculations from the start to the end of week 6 : 1. Budget at completion: 5 MARKS 2. Planned value: 5 MARKS. 3. Earned value: 5 MARKS. 4. CPI (four decimal points) AND INTERPRET THE RESULT. 2 MARKS 5. SPI (four decimal points) AND INTERPRET THE RESULT. 2 MARKS 6. What do you currently expect the total project cost to be at the end of the project? (2 MARKS) 7. From the end of week 6 , how much MORE do you expect to spend to finish the project? (2 MARKS) 8. What should be the future cost performance level required to finish the project on budget. (2 MARKS) Rrolect Planning Data Your pro ect consists of the following actlvitles and it Is planned as follows: In addition: - Labour cost Activitues A, B, and C s90ihrs. For the remaining activites \$100ihr. - An audit meeting is required to at the end of week 6 at an estimated cost of $10,000 Actual Project Performance and the end of week 6- - Activities A. B, and audit meeling are completed. - Activities C, E and G are seventy five, fifty, and twenty five percent completed respectively. - Tho totai amounl spent up to this point is $115,000. Calculations from the start to the end of week. 6 : 1. Budiget at complelion 5 MARKS 2 Planned value S MARKS. 3. Eamed value 5 MAFKS. 4. CPI (lour decimal poinlS) AND INTERPRET THERESULT 2 MARKE 5. SPI (lour decimal ponts) ANU INTERPRET THERESULT. 2 MAESS MARKS) 7 From the end of waeke, how maid wore do you oraect to spard to anish the propect (2 MARKS) MARKS\} SHOW YOUR CALCULATONS NO calcuamons nomalk: You Gan wse the HTML Eolitor to enier xom anskgn Rfn fublexil You can also insed Your project consists of the following activities and it is planned as follows: In addition: - Labour cost: Activities A, B, and C $90/hrs. For the remaining activities $100/hr. - An audit meeting is required to at the end of week 6 at an estimated cost of $10,000. Actual Project Performance and the end of week 6: - Activities A, B, and audit meeting are completed. - Activities C, E and G are seventy five, fifty, and twenty five percent completed respectively. - The total amount spent up to this point is $115,000. Calculations from the start to the end of week 6 : 1. Budget at completion: 5 MARKS 2. Planned value: 5 MARKS. 3. Earned value: 5 MARKS. 4. CPI (four decimal points) AND INTERPRET THE RESULT. 2 MARKS 5. SPI (four decimal points) AND INTERPRET THE RESULT. 2 MARKS 6. What do you currently expect the total project cost to be at the end of the project? (2 MARKS) 7. From the end of week 6 , how much MORE do you expect to spend to finish the project? (2 MARKS) 8. What should be the future cost performance level required to finish the project on budget. (2 MARKS)