Below is the data for a company with two service departments ( S1 & S2), and two production departments (P1 & P2). S1 S2 P1
Below is the data for a company with two service departments (S1 & S2), and two production departments (P1 & P2).
S1
S2
P1
P2
Budgeted OH costs
$150,000
200,000
310,000
365,000
Support work provided:
By S1
-
10%
45%
45%
By S2
15%
-
40%
45%
What is the total cost of P2 if the company uses step down method?
Step by Step Solution
There are 3 Steps involved in it
Step: 1