Below is the information pertaining to five jobs in process on October 22. Determine the sequencing of these five jobs at this machine using the
Below is the information pertaining to five jobs in process on October 22. Determine the sequencing of these five jobs at this machine using the critical ratio rule. Assume a seven-day workweek. Job Remaining Processing Time Arrival Date Due Date A 2 days Oct. 12 Oct. 29 B 6 days Oct. 15 Oct. 28 C 5 days Oct. 18 Oct. 30 D 10 days Oct. 1 Oct. 31 E 8 days Oct. 10 Oct. 27 A. A-C-B-E-D B. E-D-B-C-A C. B-E-C-D-A D. B-C-E-A-D E. None of the above