Berns University is holding a fund-raiser and will be hiring a band to entertain spectators. You have been selected to serve as the event project

Berns University is holding a fund-raiser and will be hiring a band to entertain spectators. You have been selected to serve as the event project manager and have created a Work Breakdown Structure and duration estimates for the activities involved in site preparation for the event.

Table 1

Activity No.

Description Predecessors

Duration

(in days)

A Site selection None 4
B Buy concessions A 4
C Rent facilities A 2
D Build stands A 5
E Generator & wiring installation C 2
F Security B 4
G Lighting installation E 2
H Sound system installation E, F 2
I Stage construction D 3
J Tear down G, H, I 4

Based on the information provided in Table 1, you are required to:

  1. Construct a network activity diagram for both a forward and backward pass using AON notation and calculate the estimated total duration for the project.

(6 marks)

Identify all paths through the network. Which is the critical path

Identify all burst activities and merge activities

Support your answer with references

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Business Research Methods

Authors: Emma Bell, Bill Harley, Alan Bryman

5th Edition

0198809875, 9780198809876

More Books

Students also viewed these General Management questions

Question

x-3+1, x23 Let f(x) = -*+3, * Answered: 1 week ago

Answered: 1 week ago

Question

2. In what way can we say that method affects the result we get?

Answered: 1 week ago