Question

1 Approved Answer

Black Bear Construction Company has a contract to construct a $6,000,000 bridge at an estimated cost of $5,300,000. The contract is to start in July

Black Bear Construction Company has a contract to construct a $6,000,000 bridge at an estimated cost of $5,300,000. The contract is to start in July 2017, and the bridge is to be completed in October 2019. The following data pertain to the construction period. 2017 2018 2019 Costs to date $1,325,000 $3,780,000 $5,430,000 Estimated costs to complete 3,975,000 1,620,000 Progress billings during the year 1,200,000 3,200,000 1,600,000 Cash collected during the year 1,000,000 2,340,000 2,660,000

What amount of gross profit should Black Bear recognize in 2018 using the percentage-of-completion method?

A) $270,000

B) $ 0

C)$315,000

D)$245,000

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access with AI-Powered Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Students also viewed these Accounting questions