"Blast it!" said David Wilson, president of Teledex Company. "We've just lost the bid on the Koopers job by $3,000. It seems we're either too high to get the job or too low to make any money on half the jobs we bid. Teledex Company manufactures products to customers' specifications and uses a job-order costing system. The company uses a plantwide predetermined overhead rate based on direct labor cost to apply its manufacturing overhead (assumed to be all fixed) to jobs. The following estimates were made at the beginning of the year: Manufacturing overhead Direct labor Derartment Fabricating Machining ASSEMBLY Total Plant $ 355,250 $ 406,000 $ 91,350 $ 852,600 $ 203,000 $ 101,500 $ 304,500 $ 609,000 Jobs require varying amounts of work in the three departments. The Koopers job, for example, would have required manufacturing costs in the three departments as follows: Direct materials Direct labor Manufacturing overhead Fabricating $ 3,300 $3,400 2 Department Machining $ 200 $ 500 ? Assembly $ 1,700 $6,500 7 Total Plant $ 5,200 $10,400 7 Required: 1. Using the company's plantwide approach: a. Compute the plantwide predetermined rate for the current year. b. Determine the amount of manufacturing overhead cost that would have been applied to the Koopers job. 2. Suppose that instead of using a plantwide predetermined overhead rate, the company had used departmental predetermined overhead rates based on direct labor cost. Under these conditions: a.Compute the predetermined overhead rate for each department for the current year. b. Determine the amount of manufacturing overhead cost that would have been applied to the Koopers job. 4. Assume that it is customary in the industry to bid jobs at 150% of total manufacturing cost (direct materials, direct labor, and applied overhead). a. What was the company's bid price on the Koopers job using a plantwide predetermined overhead rate? What would the bid price have been if departmental predetermined overhead rates had been used to apply overhead cost? Complete this question by entering your answers in the tabs below. Required 1A Required 18 Required 2A Required 28 Required 4A Required 48 Using the company's plantwide approach, compute the plant wide predetermined rate for the current year. Predetermined overhead rane % of direct labor coat Required 1A Required 1B > "Blast it said David Wilson, president of Teledex Company. "We've just lost the bid on the Koopers job by $3,000. It seems we're either too high to get the job or too low to make any money on half the jobs we bid." Teledex Company manufactures products to customers' specifications and uses a job-order costing system. The company uses a plantwide predetermined overhead rate based on direct labor cost to apply its manufacturing overhead (assumed to be all fixed) to jobs. The following estimates were made at the beginning of the year Manufacturing overhead Direct labor Department Fabricating Machining Assembly $ 355,250 $ Total Plant 406,000 $ 91,350 $ $ 200,000 $ 101,500 $ 304,500 $ 852,600 609,000 Jobs require varying amounts of work in the three departments. The Koopers job, for example, would have required manufacturing costs in the three departments as follows: Direct materials Direct Labor Manufacturing overhead Fabricating $ 3,300 $3,400 Department Machining $ 200 $ 500 7 Assembly $ 1,700 $ 6,500 7 Total Plant $ 5,200 $10,400 2 Required: 1. Using the company's plantwide approach: a. Compute the plantwide predetermined rate for the current year. b. Determine the amount of manufacturing overhead cost that would have been applied to the Koopers job. 2. Suppose that instead of using a plantwide predetermined overhead rate, the company had used departmental predetermined overhead rates based on direct labor cost. Under these conditions: a.Compute the predetermined overhead rate for each department for the current year. b. Determine the amount of manufacturing overhead cost that would have been applied to the Koopers job. 4. Assume that it is customary in the industry to bid jobs at 150% of total manufacturing cost (direct materials, direct labor, and applied overhead) a.What was the company's bid price on the Koopers job using a plantwide predetermined overhead rate? b. What would the bid price have been if departmental predetermined overhead rates had been used to apply overhead cost? Complete this question by entering your answers in the tabs below. Required 1A Required 1B Required 2A Required 2B Required 4A Required 48 Using the company's plantwide approach, determine the amount of manufacturing overhead cost that would have been applied to the Koopers job. Manufacturing overhead cost applied RowLA Rewind "Blast it' said David Wilson, president of Teledex Company. "We've just lost the bid on the Koopers job by $3.000. It seems we're either too high to get the job or too low to make any money on half the jobs we bid." Teledex Company manufactures products to customers' specifications and uses a job-order costing system. The company uses a plantwide predetermined overhead rate based on direct labor cost to apply its manufacturing overhead (assumed to be all fixed) to jobs. The following estimates were made at the beginning of the year Department Tabricating Machining Assembly Total Plant Manufacturing overhead $ 355,250 $ 406,000 $ 91,350 $ 852,600 Direct labor $ 203,000 $ 101,500 $ 304,500 5 609,000 Jobs require varying amounts of work in the three departments. The Koopers job, for example, would have required manufacturing costs in the three departments as follows: Direct materials Direct Labor Manufacturing overhead Fabricating $3,300 $3,400 7 Department Machining $ 200 $ 500 ? Assembly $ 1.700 $6,500 7 Total Plant $ 5,200 $10,400 1 Required: 1. Using the company's plantwide approach: a. Compute the plantwide predetermined rate for the current year. b. Determine the amount of manufacturing overhead cost that would have been applied to the Koopers job 2. Suppose that instead of using a plantwide predetermined overhead rate, the company had used departmental predetermined overhead rates based on direct labor cost. Under these conditions: a.Compute the predetermined overhead rate for each department for the current year b. Determine the amount of manufacturing overhead cost that would have been applied to the Koopers job. 4. Assume that it is customary in the industry to bid jobs at 150% of total manufacturing cost direct materials, direct labor, and applied overhead). a What was the company's bid price on the Koopers job using a plantwide predetermined overhead rate? b.What would the bid price have been if departmental predetermined overhead rates had been used to apply overhead cost? Complete this question by entering your answers in the tabs below. Required 1A Required 10 Required 2A Required 28 Required 4A Required 4B Suppose that instead of using a plantwide predetermined overhead rate, the company had used departmental predetermined overhead rates based on direct labor cost. Compute the predetermined overhead rate for each department for the current year. Predetermined Overhead Rate Fabricating department % Machining department Assembly department X of direct labor cost of direct labor cost of direct labor cost Blast i said David Wilson, president of Teledex Company. "We've just lost the bid on the Koopers job by $3,000. It seems we're either too high to get the job or too low to make any money on half the jobs we bid." Teledex Company manufactures products to customers' specifications and uses a job-order costing system. The company uses a plantwide predetermined overhead rate based on direct labor cost to apply its manufacturing overhead (assumed to be all fixed) to jobs. The following estimates were made at the beginning of the year Manufacturing overhead Direct labor Fabricating Machining 5 355,250 $ 406,000 $ 200,000 $ 101,500 Mebly Total Plant $ 91,350 852.600 $ 304,500 5 609,000 Jobs require varying amounts of work in the three departments. The Koopers job, for example, would have required manufacturing costs in the three departments as follows: Direct materials Direct labor Maracturing overhead Fabricating $ 3,300 $3,400 1 Department Machining $ 200 500 2 sembly $1,700 $ 6,500 Total plant $ 5,200 510.400 Required: 1. Using the company's plantwide approach a. Compute the plantwide predetermined rate for the current year b. Determine the amount of manufacturing overhead cost that would have been applied to the Koopers job. 2. Suppose that instead of using a plantwide predetermined overhead rate, the company had used departmental predetermined overhead rates based on direct labor cost. Under these conditions: a. Compute the predetermined overhead rate for each department for the current year b. Determine the amount of manufacturing overhead cost that would have been applied to the Koopers job. 4 Assume that it is customary in the industry to bid jobs at 150% of total manufacturing cost (direct materials, direct labor, and applied overhead a What was the company's bid price on the Koopers job using a plantwide predetermined overhead rate? b.What would the bid price have been if departmental predetermined overhead rates had been used to apply overhead cost? Complete this question by entering your answers in the tabs below. Required 1A Required 18 Required 2A Required 28 Required 4A Required 4B Suppose that instead of using a plantwide predetermined overhead rate, the company had used departmental predetermined overhead rates based on direct labor cost. Determine the amount of manufacturing overhead cost that would have been applied to the Koopers job. Manufacturing overhead cost applied F!! Next > "Blast It" said David Wilson, president of Teledex Company. We've just lost the bid on the Koopers job by $3,000. It seems we're elther too high to get the job or too low to make any money on half the jobs we bid." Teledex Company manufactures products to customers' specifications and uses a job-order costing system. The company uses a plantwide predetermined overhead rate based on direct labor cost to apply its manufacturing overhead (assumed to be all fixed) to jobs. The following estimates were made at the beginning of the year: Manufacturing overhead Direct labor Department Fabricating Machining Assembly Total Plant $ 355,250 $ 406,000 91,350 $ 852,600 $ 200,000 $ 101,500 $ 104,500 $ 609,000 Jobs require varying amounts of work in the three departments. The Koopers job, for example, would have required manufacturing costs in the three departments as follows: Direct materials Direct labor Manufacturing overhead Fabricating $ 3,300 $3,400 7 Department Machining $ 200 $ 500 ? Assembly $ 1,700 $6,500 7 Total Plant $ 5,200 $10,400 ? Required: 1. Using the company's plantwide approach: a. Compute the plantwide predetermined rate for the current year. b. Determine the amount of manufacturing overhead cost that would have been applied to the Koopers job. 2. Suppose that instead of using a plantwide predetermined overhead rate, the company had used departmental predetermined overhead rates based on direct labor cost. Under these conditions: a.Compute the predetermined overhead rate for each department for the current year. b. Determine the amount of manufacturing overhead cost that would have been applied to the Koopers job. 4. Assume that it is customary in the industry to bid jobs at 150% of total manufacturing cost (direct materials, direct labor, and applied overhead). a. What was the company's bid price on the Koopers job using a plantwide predetermined overhead rate? b.What would the bid price have been If departmental predetermined overhead rates had been used to apply overhead cost? Complete this question by entering your answers in the tabs below. Required 1A Required 16 Required 2A Required 28 Required 4A Required 48 Assume that it is customary in the industry to bid jobs at 150% of total manufacturing cost (direct materials, direct labor, and applied overhead). What was the company's bid price on the Koopers job using a plantwide predetermined overhead rate? Company's bid price "Blast It" said David Wilson, president of Teledex Company. We've just lost the bid on the Koopers job by $3,000. It seems we're either too high to get the job or too low to make any money on half the jobs we bid." Teledex Company manufactures products to customers' specifications and uses a job-order costing system. The company uses a plantwide predetermined overhead rate based on direct labor cost to apply its manufacturing overhead (assumed to be all fixed) to jobs. The following estimates were made at the beginning of the year: Manufacturing overhead Direct labor Department Fabricating Machining Assembly Total Plant $ 355,250 $ 406,000 $ 91,350 $ 852,600 $ 203,000 $ 101,500 $ 104,500 $ 609,000 Jobs require varying amounts of work in the three departments. The Koopers job, for example, would have required manufacturing costs in the three departments as follows: Direct materials Direct Labor Manufacturing overhead Fabricating $3,300 $ 3,400 2 Department Machining $ 200 $ 500 Assembly $ 1,700 $6,500 7 Total Plant $ 5,200 $10,400 7 Required: 1. Using the company's plantwide approach a. Compute the plantwide predetermined rate for the current year. b. Determine the amount of manufacturing overhead cost that would have been applied to the Koopers job. 2. Suppose that instead of using a plantwide predetermined overhead rate, the company had used departmental predetermined overhead rates based on direct labor cost. Under these conditions: a.Compute the predetermined overhead rate for each department for the current year. b. Determine the amount of manufacturing overhead cost that would have been applied to the Koopers job. 4. Assume that it is customary in the industry to bid jobs at 150% of total manufacturing cost direct materials, direct labor, and applied overhead) a What was the company's bid price on the Koopers job using a plantwide predetermined overhead rate? bWhat would the bid price have been if departmental predetermined overhead rates had been used to apply overhead cost? Complete this question by entering your answers in the tabs below. Required 1A Required 18 Required 2A Required 28 Required 4 Required 40 Assume that it is customary in the industry to bid jobs at 150% of total manufacturing cost (direct materials, direct labor, and applied overhead). What would the bid price have been if departmental predetermined overhead rates had been used to apply overhead cost? Manufacturing overhead cost applied