"Blast iti" said David Wilson, president of Teledex Company. "We've just lost the bid on the Koopers job by $3,000. It seems we're either too high to get the job or too low to make any money on half the jobs we bid." Teledex Company manufactures products to customers' specifications and uses a job-order costing system. The company uses a plantwide predetermined overhead rate based on direct labor cost to apply its manufacturing overhead (assumed to be all fixed) to jobs. The following estimates were made at the beginning of the year. Department Fabricating Machining Assembly Total Plant Manufacturing overhead $ 379,758 $ 434,800 $ 97,650 $911,400 Direct labor $ 217,800 $ 108,500 $ 325,500 $ 651,600 Jobs require varying amounts of work in the three departments. The Koopers job, for example, would have required manufacturing costs in the three departments as follows: Direct materials Direct labor Manufacturing overhead Fabricating $4,700 $6,200 7 Department Machining $300 5 600 Assembly $3,100 $7,900 Total Plant $ 8,100 $14.700 Required: 1. Using the company's plantwide approach: a. Compute the plantwide predetermined rate for the current year. b. Determine the amount of manufacturing overhead cost that would have been applied to the Koopers job. 2. Suppose that instead of using a plantwide predetermined overhead rate, the company had used departmental predetermined overhead rates based on direct labor cost. Under these conditions: a. Compute the predetermined overhead rate for each department for the current year. b. Determine the amount of manufacturing overhead cost that would have been applied to the Koopers job 4 Assume that it is customary in the industry to bid jobs at 150% of total manufacturing cost (direct materials, direct labor, and applied overhead) What was the company's bid price on the Koopers job'using a plantwide predetermined overhead rate? b. What would the bid price have been if departmental predetermined overhead rates had been used to apply overhead cost? Complete this question by entering your answers in the tabs below. Required 1A Required 16 Required 2A Required 28 Required 4 Required 48 Using the company's plantwide approach, compute the plantwide predetermined rate for the current year, Predetermined overhendra of direct labor cost Required: 1. Using the company's plantwide approach: a. Compute the plantwide predetermined rate for the current year b. Determine the amount of manufacturing overhead cost that would have been applied to the Koopers job 2. Suppose that instead of using a plantwide predetermined overhead rate, the company had used departmental predetermined overhead rates based on direct labor cost. Under these conditions: a. Compute the predetermined overhead rate for each department for the current year. b. Determine the amount of manufacturing overhead cost that would have been applied to the Koopers job 4. Assume that it is customary in the industry to bid jobs at 150% of total manufacturing cost (direct materials, direct labor, and applied overhead) a. What was the company's bid price on the Koopers job using a plantwide predetermined overhead rate? b. What would the bid price have been it departmental predetermined overhead rates had been used to apply overhead cost? Complete this question by entering your answers in the tabs below. Required 1A Reruired 15 Required 2A Required 28 Required 4A Required 48 Using the company's plantwide approach, determine the amount of manufacturing overhead cost that would have been applied to the Koopers job Manufacturing ved copied Required: 1. Using the company's plantwide approach: Compute the plantwide predetermined rate for the current year. b. Determine the amount of manufacturing overhead cost that would have been applied to the Koopers job. 2. Suppose that instead of using a plantwide predetermined overhead rate, the company had used departmental predetermined overhead rates based on direct labor cost. Under these conditions: a. Compute the predetermined overhead rate for each department for the current year b. Determine the amount of manufacturing overhead cost that would have been applied to the Koopers job. 4. Assume that it is customary in the industry to bid jobs at 150% of total manufacturing cost (direct materials, direct labor, and applied overhead) a. What was the company's bid price on the Koopers job using a plantwide predetermined overhead rate? b. What would the bid price have been if departmental predetermined overhead rates had been used to apply overhead cost? Complete this question by entering your answers in the tabs below, Required 1A Required 18 Required 2A Required 28 Required 4 Required 48 Suppose that instead of using a plantwide predetermined overhead rate, the company had used departmental predetermined overhead rates based on direct labor cost. Compute the predetermined overhead rate for each department for the current year, Predetermined Overhead Rate Fabricating department of direct labor cost Machining department of direct labor cost Assembly department of direct labor cost Required: 1. Using the company's plantwide approach: a. Compute the plantwide predetermined rate for the current year. b. Determine the amount of manufacturing overhead cost that would have been applied to the Koopers job. 2. Suppose that instead of using a plantwide predetermined overhead rate, the company had used departmental predetermined overhead rates based on direct labor cost. Under these conditions: a. Compute the predetermined overhead rate for each department for the current year b. Determine the amount of manufacturing overhead cost that would have been applied to the Koopers job. 4. Assume that it is customary in the industry to bid jobs at 150% of total manufacturing cost (direct materials, direct labor, and applied overhead) What was the company's bid price on the Koopers job using a plantwide predetermined overhead rato? b. What would the bid price have been it departmental predetermined overhead rates had been used to apply overhead cost? Complete this question by entering your answers in the tabs below. Required 1A Required 18 Required 2A Required Reed 4 Required 4 Suppose that instead of using a plantwide predetermined overhead rate, the company had used departmental predetermined overhead rates based on direct labor cost. Determine the amount of manufacturing overhead cost that would have been applied to the Koopers job. Manufacturing that cost applied equired: Using the company's plantwide approach: Compute the plantwide predetermined rate for the current year Determine the amount of manufacturing overhead cost that would have been applied to the Koopers job. Suppose that instead of using a plantwide predetermined overhead rate, the company had used departmental predetermined Overhead rates based on direct labor cost. Under these conditions: e Compute the predetermined overhead rate for each department for the current year. . Determine the amount of manufacturing overhead cost that would have been applied to the Koopers job. 4. Assume that it is customary in the industry to bid jobs at 150% of total manufacturing cost (direct materials, direct labor, and applied a. What was the company's bid price on the Koopers job using a plantwide predetermined overhead rate? b. What would the bid price have been if departmental predetermined overhead rates had been used to apply overhead cost? Complete this question by entering your answers in the tabs below. Required 1A Required 18 Required 2A Required 20 Required 4 Required 40 Assume that its customary in the industry to bid jobs at 150% of total manufacturing cost direct materials direct labor and applied overhead). What was the company's bid price on the Koopers Job using a partide predetermined overhead rate Required: 1. Using the company's plantwide approach: a. Compute the plantwide predetermined rate for the current year. b. Determine the amount of manufacturing overhead cost that would have been applied to the Koopers job 2. Suppose that instead of using a plantwide predetermined overhead rate, the company had used departmental predetermined overhead rates based on direct labor cost. Under these conditions: a. Compute the predetermined overhead rate for each department for the current year. b. Determine the amount of manufacturing overhead cost that would have been applied to the Koopers job. 4. Assume that it is customary in the industry to bid jobs at 150% of total manufacturing cost (direct materials, direct labor, and applied overhead) a. What was the company's bid price on the Koopers job using a plantwide predetermined overhead rate? b. What would the bid price have been if departmental predetermined overhead rates had been used to apply overhead cost? Complete this question by entering your answers in the tabs below. Required 1A Required 16 Required 2A Required 2 Required 4 Require 40 Assume that it is customary in the industry to bid jobs at 150% of total manufacturing cost (direct materials, direct labor, and applied overhead). What would the bid price have been ir departmental predetermined overhead rates had been used to apply overhad cost? Manufacturing overhead cout applied