Bloopers analysts have come up with the following revised estimates for its magnoosium mine: Range Pessimistic Optimistic Initial investment + 40 % 20 % Revenues

Bloopers analysts have come up with the following revised estimates for its magnoosium mine:

Range

Pessimistic Optimistic
Initial investment + 40 % 20 %
Revenues 20 % + 25 %
Variable costs + 20 % 15 %
Fixed cost + 50 % 50 %
Working capital + 35 % 35 %

Conduct a sensitivity analysis for each variable and range and compute the NPV for each. Use Spreadsheet 10.1 and accompanying data as a starting point for the analysis. (Do not round intermediate calculations. Negative amounts should be indicated by a minus sign. Enter your answers in thousands rounded to the nearest whole dollar.)

image text in transcribedimage text in transcribed

A Inputs Initial investment ($ thousands) Salvage value ($ thousands) Initial revenues ($ thousands) Variable costs (% of revenues) Initial fixed costs ( thousands) Inflation rate (96) Discount rate (95) Receivables (% of sales) Inventory (% of next year's costs) Tax rate (%) 15,000 2,000 15,000 40.0% 4,000 5.096 12.0% 16.7% 15.0% 21.0% Year: 0 15,000 B. Fixed assets Investments in fixed assets Sales of fixed assets Cash flow from fixed assets -15,000 1,580 1,580 15,000 6,000 C. Operating cash flow Revenues Variable expenses Fixed expenses Depreciation Pretax profit Tax Profit after tax Operating cash flow 3,000 2,000 420 1,580 4,580 15,750 6,300 4,200 3,000 2,250 473 1,778 4,778 16,538 6,615 4,410 3,000 2,513 528 1,985 4,985 1 7,364 6,946 4,631 3,000 2,788 586 2,203 5,203 18,233 7,293 4,862 3,000 3,078 646 2,431 5,431 D. Working capital Working capital Change in working capital Cash flow from investment in working capital 4,279 1.500 1,500 -1,500 204 4.075 2.575 -2,575 0.408 4,493 214 -214 0.408 4,717' 225 -225 0.408 3,039 -1,679 1,679 0.250 0 3,039 3,039 -204 0.408 E. Project valuation Total project cash flow Discount factor PV of cash flow Net present value - 16,500 1.000 - 16,500 1,870.1 2,005 0.893 1,790 4,574 0.797 3,646 4,771 0.712 3,396 0 4,978 .636 3,164 7,110 0.567 4,034 4,619 0.507 2,340 Project NPV Expected Pessimistic Optimistic Initial investment Revenues Variable costs Fixed costs Working capital A Inputs Initial investment ($ thousands) Salvage value ($ thousands) Initial revenues ($ thousands) Variable costs (% of revenues) Initial fixed costs ( thousands) Inflation rate (96) Discount rate (95) Receivables (% of sales) Inventory (% of next year's costs) Tax rate (%) 15,000 2,000 15,000 40.0% 4,000 5.096 12.0% 16.7% 15.0% 21.0% Year: 0 15,000 B. Fixed assets Investments in fixed assets Sales of fixed assets Cash flow from fixed assets -15,000 1,580 1,580 15,000 6,000 C. Operating cash flow Revenues Variable expenses Fixed expenses Depreciation Pretax profit Tax Profit after tax Operating cash flow 3,000 2,000 420 1,580 4,580 15,750 6,300 4,200 3,000 2,250 473 1,778 4,778 16,538 6,615 4,410 3,000 2,513 528 1,985 4,985 1 7,364 6,946 4,631 3,000 2,788 586 2,203 5,203 18,233 7,293 4,862 3,000 3,078 646 2,431 5,431 D. Working capital Working capital Change in working capital Cash flow from investment in working capital 4,279 1.500 1,500 -1,500 204 4.075 2.575 -2,575 0.408 4,493 214 -214 0.408 4,717' 225 -225 0.408 3,039 -1,679 1,679 0.250 0 3,039 3,039 -204 0.408 E. Project valuation Total project cash flow Discount factor PV of cash flow Net present value - 16,500 1.000 - 16,500 1,870.1 2,005 0.893 1,790 4,574 0.797 3,646 4,771 0.712 3,396 0 4,978 .636 3,164 7,110 0.567 4,034 4,619 0.507 2,340 Project NPV Expected Pessimistic Optimistic Initial investment Revenues Variable costs Fixed costs Working capital

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

A Fast And Frugal Finance

Authors: William P. Forbes, Aloysius Igboekwu, Shabnam Mousavi

1st Edition

0128124954, 978-0128124956

More Books

Students also viewed these Finance questions

Question

8. Explain the contact hypothesis.

Answered: 1 week ago

Question

2. Define the grand narrative.

Answered: 1 week ago