Blue Box Beach Chairs has the following standards to make beach chairs: Standard Quantity Standard Price Direct materials2.2 pounds of polywood per chair $3.50 per
Blue Box Beach Chairs has the following standards to make beach chairs:
Standard Quantity Standard Price
Direct materials2.2 pounds of polywood per chair $3.50 per pound
Direct labor0.65 hours per chair $13.00 per hour
The static budget was based on the production of 6,200 beach chairs. The company used 13,000 pounds of polywood in order to make 6,000 chairs in April. The company purchased 7,000 pounds of polywood at a total cost of $24,150. It also used 3,840 labor hours at a cost of $12.70 per hour. How much is the direct labor efficiency variance?
A $1,932 unfavorable
B $1,152 favorable
C $780 favorable
D $2,470 favorable
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started