Blue Hamster Manufacturing Inc. is a small firm, and several of its managers are worried about how soon the firm will be able to recover
Blue Hamster Manufacturing Inc. is a small firm, and several of its managers are worried about how soon the firm will be able to recover its initial investment from Project Omega's expected future cash flows. To answer this question, Blue Hamster's CFO has asked that you compute the project's payback period using the following expected net cash flows and assuming that the cash flows are received evenly throughout each year.
Complete the following table and compute the project's conventional payback period. For full credit, complete the entire table.
Year 0 | Year 1 | Year 2 | Year 3 | |
Expected cash flow | -4,000,000 | $ 1,600,000 | $ 3,400,000 | $1,400,000 |
Cumulative cash flow | ||||
Conventional payback period | NA | NA | NA | |
The conventional payback period ignores the time value of money, and this concerns Blue Hamster's CFO. He has now asked you to compute Omega's discounted payback period, assuming the company has a 8% cost of capital. Complete the following table and perform any necessary calculations. Round the discounted cash flow values to the nearest whole dollar, and the discounted payback period to the nearest two decimal places. For full credit, complete the entire table.
Year 0 | Year 1 | Year 2 | Year 3 | |
Cash flow | -4,000,000 | $ 1,600,000 | $ 3,400,000 | $1,400,000 |
Discounted cash flow | ||||
Cumulative discounted cash flow | ||||
Discounted payback period: | NA | NA | NA |
Which version of a project's payback period should the CFO use when evaluating Project Omega, given its theoretical superiority?
1. The regular paback period, OR
2. The discounted payback period
One theoretical disadvantage of both payback methods - compared to the net present value method - is that they fail to consider the value of the cash flows beyond the point in time equal to the payback period.
How much value does the discounted payback period method fail to recognize due to this theoretical deficiency?
1. $ 2,592,846
2. $ 1,507,798
3. $ 1,111,365
4. $ 4, 026,317
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started