Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

Blueprint Problem: Activity-based costing Activity-Based Costing Traditionally, overhead costs are assigned based arbitrarily on the rate of either direct labor or direct materials associated with

Blueprint Problem: Activity-based costing

Activity-Based Costing

Traditionally, overhead costs are assigned based arbitrarily on the rate of either direct labor or direct materials associated with production. This makes sense when companies only make a few products, production processes are simple, and overhead costs are less pervasive. However, today production processes are more complex, companies make a wider array of products, and fewer costs are directly traceable to units of production. To address this, companies use activity-based costing (ABC).

Specifically, activity-based costing identifies and traces costs and expenses to activities and then to specific products. ABC uses multiple factory overhead rates based on activities. Activities are the types of work, or actions, involved in a manufacturing process or service activity. For example, assembly, inspection, and engineering design are activities.

The estimated activity costs are allocated to products using an activity rate. Activity rates are determined as follows: Activity Rate = Estimated Activity Cost / Estimated Activity Base Usage

Illustrated Example of Activity-Based Costing

Comparing Two Products under Traditional and Activity-Based Costing

Compare two projects under development by the same company. The following are a few aspects of each product's development process relevant to costs.

Product A Product B
Requires 4,000 hours of testing Requires 1,000 hours of testing
Requires 5,320 units of computing power Requires 2,280 units of computing power
Requires 25 developer hours to implement Requires 75 developer hours to implement
Cost Items Cost of Each Activity
Testing: $25,600
Computing power: $38,400
Developer hourly cost: $13 per hour

Traditional Costing

Traditional costing would take the proportion of a direct cost, such as direct labor hours, and use it as the basis for allocating overhead costs, such as computing power and testing. In the following table, use developer hours as the basis for assigning overhead costs (computing and developer costs) to each project If required, round your answers to the nearest dollar.

Product A Product B
Percentage of developer hours 25% Percentage of developer hours 75%
Testing cost $ Testing cost $
Computing cost $ Computing cost $
Developer cost $ Developer cost $
Total cost $ Total cost $

Percentage of developer hours

+ Percentage of developer hours for Product A (25%)

+ Percentage of developer hours for Product B (75%)

Seeing how many resources each product (A and B) requires for production compared to the costs calculated under traditional costing, does traditional costing serve as an accurate gauge of costs? SelectYesNoNot enough informationCorrect 9 of Item 1

Hide Feedback

Correct

Check My Work Feedback

Using traditional cost assignment means pegging overhead costs based on a direct cost, such as direct labor or direct materials. In this case, you use direct labor (developer hours) as the basis for overhead allocation.

For product A, the percentage of developer labor costs as a proportion of the whole is already calculated. This is the figure that, when multiplied by the overhead values, will yield the overhead assigned to each project under traditional costing.

Activity-Based Costing

Using the data above for products A and B, calculate the costs using activity-based costing. Allocate the costs of testing, computing, and development based on the rates of activity consumed by each product's development process. If required, in your computations, round per unit costs to the nearest cent. Round your final answers to the nearest dollar.

Cost Activity Base
Testing Hours of testing
Computing cost Units of computing power
Developer cost Development hours

Product A Product B
Testing cost $ Testing cost $
Computing cost $ Computing cost $
Developer cost $ Developer cost $
Total cost $ Total cost $

Hide Feedback

Partially Correct

Check My Work Feedback

The budgeted activity costs are assigned to products using factory overhead rates for each activity. These rates are called activity rates because they are related to activities. Activity rates are determined as follows: Activity Rate = Budgeted Activity Cost / Total Activity Base Usage

The costs are allocated to the product by multiplying the activity-base usage by the computed activity rate.

Activity-based costing for varying batch production

A manufacturing company has the following two activities associated with completion of products:

The setting up of machines for running batches of products

The actual production of units produced

The company has annual manufacturing overhead costs of $2,000,000, of which $200,000 is directly involved in setting up machines for batch runs. During the year, the company expects to perform 400 machine setups, one setup per batch for a total of 400 batches of production. Assume that the batch sizes vary considerably, but the work involved in setting up the machines is not appreciably different from one job to the next.

If the company estimates that the $200,000 costs associated with setups will yield 400 setups this year, the cost associated directly with each setup will be $ per setup. Because each job will require its own setup, setup costs are viewed as batch costs. Because $200,000 of the $2,000,000 are costs associated with setups, this means that costs associated directly with the production of units equal $ .

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Fundamentals Of Accounting And Financial Analysis

Authors: Anil Chowdhury

1st Edition

9788131702024, 9788131776070

More Books

Students also viewed these Accounting questions

Question

2 What are the psychological stages of coping with change?

Answered: 1 week ago

Question

6 Why is change considered a central aspect of HRM practice?

Answered: 1 week ago