Question
Boat-on-water uses a standard cost system for materials and labor in producing small fishing boats. Production requires fiberglass, paint and a purchased trim package as
Boat-on-water uses a standard cost system for materials and labor in producing small fishing boats. Production requires fiberglass, paint and a purchased trim package as well as direct as follows:
Standard Costs for Variable Costs |
|
1,000 pounds of fiberglass @ $2.00 per pound | $2,000 |
40 hours of labor @ $25 per hour | 1,000 |
40 hours of labor @ $40 per direct labor hour | 1,600 |
The following actual data related to the production of 100 boats was recorded in January
Materials Purchased on Account |
Fiberglass 800,000 pounds @$1.83 per pound |
Materials Used |
Fiberglass 980,000 pounds |
Direct Labor Used |
3,900 hours @ $23.50 per hour |
Variable Manufacturing Overhead |
$175,000 total Variable Manufacturing Overhead |
REQUIRED:
- Determine the direct materials price and efficiency variances for Fiberglass.
- Prepare the journal entries for fiberglass
- Determine the direct labor price and efficiency variances
- Prepare the direct labor journal entries
- Determine the direct labor price and efficiency variances if direct labor is fixed and we made 110 boats.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started