Question
Bold Company manufactures surfboards.Its standard cost information follows: Standard Standard Price Standard Unit Quantity (Rate) Cost Fiberglass 15 sq. ft. $5 per sq. ft. $75.00
Bold Company manufactures surfboards.Its standard cost information follows:
Standard Standard Price Standard Unit
Quantity (Rate) Cost
Fiberglass 15 sq. ft. $5 per sq. ft. $75.00
Direct labor 10 hrs $15 per hour 150.00
Variable manufacturing overhead $6 per direct labor hour. 60.00
Fixed manufacturing overhead $8 per direct labor hour 80.00
The company expected to require 2,500 hours of direct labor.
Bold has the following actual results for the month of June:
Number of units produced and sold 260
Number of square feet of fiberglass used 4,100
Cost of fiberglass purchased (5,000 square feet) $24,500
Number of labor hours worked 2,550
Direct labor cost $39,525
Variable overhead cost $14,790
Fixed overhead cost $20,500
Required:
a) Compute the eight variances
b) Explain what these variances may be indicating.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started