Bolsa Corporation produces high-quality leather belts. The company's plant in Boise uses a standard costing system and has set the following standards for materials and
Bolsa Corporation produces high-quality leather belts. The company's plant in Boise uses a standard costing system and has set the following standards for materials and labor:
Leather (5 strips @ $2.00) | $10.00 |
Direct labor (1 hr. @ $9.00) | 9.00 |
Total prime cost | $19.00 |
During the first month of the year, Boise plant produced 39,000 belts. Actual leather purchased was 120,000 strips at $3.10 per strip. There were no beginning or ending inventories of leather. Actual direct labor was 36,000 hours at $16.00 per hour.
Required:
1. Compute the costs of leather and direct labor that should be incurred for the production of 39,000 leather belts.
Materials | $ |
Labor | $ |
2. Compute the total budget variances for materials and labor.
Total Budget Variance | ||
Materials | $ | |
Labor | $ |
3. Conceptual Connection: Would you consider these variances material with a need for investigation?
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started