Question
BR Piling Pte Ltd was contracted to install bored piles and construct a basement carnpark for a13-storybuildinginSingapore.Thepilingcontractorcompletedtheworksandhandedthesiteto the architect by the stipulated deadline. The architect
BR Piling Pte Ltd was contracted to install bored piles and construct a basement carnpark for a13-storybuildinginSingapore.Thepilingcontractorcompletedtheworksandhandedthesiteto the architect by the stipulated deadline. The architect was engaged by the owner and wasresponsibleforthedesign andsupervisionofworksfortheentire project.Twoweekslater,theproject's superstructure work was awarded to another contractor, KC Contractors at a lumpsumpriceof$25million usingtheSIALumpSumcontract(9thEdition).Thecontract durationis12 months commencingfrom 1st Jan 2020.
During the tender period, KC Contractors decided not to purchase a specific type ofglass for the project's cladding work because there was no place to store the materialand it would not be needed until months later after construction had progressed. The contract specified a particular brand for the glass that had to be purchased from amanufacturerinBelgium.Thecontractalsospecifiedthatthecontractorwasentitledtoproposealternativetypesofglassbuttheymustbeofequivalentquality.WhenKCContractorsmadetheglassorderedfromtheBelgium manufacturer;thepricehadrisen by30 percentcompared to thetenderprice.
Discussthecourseactions availabletothearchitectandKCContractorsincludingtheimplications.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started