Brace Kenny company is the leader in manufacturing of canned meats. The CEO of Brace Kenny has challenged his Vice President to erect a new
Brace Kenny company is the leader in manufacturing of canned meats. The CEO of Brace Kenny has challenged his Vice President to erect a new plant in St.Elizabeth within 36 days. His Vice President Mr. Owen has set out the activities, associated, times and relationship between the activities in the table below.
TIME IN DAYS | IMMEDIATE | |||
ACTIVITY | a | m | b | PREDECESSOR |
A | 6 | 8 | 9 | -- |
B | 9 | 12 | 15 | -- |
C | 4 | 6 | 11 | A,B |
D | 3 | 4.5 | 6 | B |
E | 1 | 2 | 3 | A |
F | 1 | 3 | 5 | C |
G | 5 | 6 | 10 | E,F |
H | 2 | 3 | 4 | D,F |
I | 1 | 1 | 1 | G,H |
J | 5 | 12 | 10 | I |
- Calculate the expected duration of each activity and place in the table below 5 Marks
Activity | A | B | C | D | E | F | G | H | I | J |
Expected Time |
- Draw the network 4 Marks
- Develop the activity schedule for the project 5 Marks
- What is project completion time 3 Marks
- What are the critical activities 3 Marks
What is probability that the plant will be complete within 36 days in St. Elizabeth.
5 Marks
NB. Please show working
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started