Question
.Bright Window Company designs and builds custom windows for luxury homes. Most of the windows are custom made but occasionally the company does mass production
.Bright Window Company designs and builds custom windows for luxury homes. Most of the windows are custom made but occasionally the company does mass production on order. Its budgeted manufacturing overhead costs for the year 2011 are as follows:
Overhead Cost Pools Amount
Purchasing $ 180,000
Production (cutting, milling, finishing) 400,000
Setting up machines 135,000
Inspecting 160,000
Utilities 300,000
Total budget overhead costs $1,175,000
For the last three years, the company has been charging overhead to products on the basis of machine hours. For the year 2011, 100,000 machine hours are budgeted.
Susan Craft, owner-manager of Bright Window, recently directed her accountant to implement the activity-based costing system she has repeatedly proposed. At Susan's request, the accountant and production foreman identify the following cost drivers and their usage for the previously budgeted overhead cost pools.
Overhead Cost Pools Activity Cost Drivers Total Drivers
Purchasing Number of orders 500
Production (cutting, milling, finishing) Direct labor hours 80,000
Setting up machines Number of setups 1,000
Inspecting Number of inspections 5,000
Utilities Square feet occupied 75,000
During this month, the company received an order for 50 window sets from a housing development contractor. The accountant prepares cost estimates for producing components for 50 window sets so Susan can submit a contract price per window set to the contractor. The following data for the production of 50 window sets is accumulated:
Direct materials $120,000
Direct labor $135,000
Machine hours 12,000
Direct labor hours 10,000
Number of purchase orders 50
Number of machine setups 80
Number of inspections 380
Number of square feet occupied 7,000
Instructions
(a) Compute the predetermined overhead rate using traditional costing with machine hours as the basis.
(b) Compute the manufacturing cost per window set under traditional costing.
(c) Compute the manufacturing cost per window set under the proposed activity-based costing.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started