Brook's law say that adding more people to a late project: 1. is essential whenever projects are late. 2. reduces total payroll costs. 3. tends
Brook's law say that adding more people to a late project: 1. is essential whenever projects are late. 2. reduces total payroll costs. 3. tends to further delay the project. 4. improves team cohesion. 5. strengthens team norms that support productivity