Buckley Manufacturing reported the following budgeted and actual figures for one of its products: Standard overhead cost per unit (1 hour at $2.75 per hour)
Buckley Manufacturing reported the following budgeted and actual figures for one of its products: Standard overhead cost per unit (1 hour at $2.75 per hour) $2.75 Actual overhead costs Budgeted units Actual units produced $4,800 525 400 Given this data, what is the total variable overhead variance for this product? O A. $3,356 favorable OB. $3,700 unfavorable OC. $3,356 unfavorable OD. $3,700 favorable