Question

1 Approved Answer

Budgeted Cost Actual Costs Materials (per tire): 12 lbs at $1.80/lb Total Materials purchased: 840,000 lbs Labor (per tire): 4 hrs at $14/hr Total Cost

Budgeted Cost Actual Costs
Materials (per tire): 12 lbs at $1.80/lb Total Materials purchased: 840,000 lbs
Labor (per tire): 4 hrs at $14/hr Total Cost of purchase: $1,554,000
Factory O/H (per tire): 3 hrs at $8/hr Total Material Used: 849,600 lbs
Labor (per tire): 4.1 hrs at $13/hr
Factory O/H (per tire): 2.8 hrs at $8.50/hr

The budgeted and actual costs at Goodyear Company is as above.

During the month of October, Goodyear produced 72,000 tires.

Please determine the following (A-E) based on the information given.

A) The budgeted and actual cost, respectively, of producing one tire (to the nearest $)

B) The Direct Labor Efficiency Variance

C) The Direct Materials Quantity Variance

D) The Direct Materials Price Variance

E) The Labor Rate Variance

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Financial Shenanigans

Authors: Howard Schilit

2nd Edition

0071386262, 9780071386265

More Books

Students also viewed these Accounting questions

Question

1. To generate a discussion on the concept of roles

Answered: 1 week ago

Question

6. What information processes operate in communication situations?

Answered: 1 week ago