BuffaloConstruction Company uses the percentage-of-completion method of accounting. In 2017, Buffalo began work under contract #E2-D2, which provided for a contract price of $2,227,000. Other
BuffaloConstruction Company uses the percentage-of-completion method of accounting. In 2017, Buffalo began work under contract #E2-D2, which provided for a contract price of $2,227,000. Other details follow:
2017 2018
Costs incurred during the year $647,600 $1,405,000
Estimated costs to complete, as of December 31 971,400 -0-Billings to date 415,000 2,227,000
Collections during the year 353,000 1,523,000
What portion of the total contract price would be recognized as revenue in 2017? In 2018?
Revenue recognized in 2017 $ 890,800
Revenue recognized in 2018 $1,336,200
Assuming the same facts as those above except that Buffalo uses the completed-contract method of accounting, what portion of the total contract price would be recognized as revenue in 2018?
Revenue recognized in 2018 $2,227,000
****Need assistance with problem in attachment ****
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started