Question

1 Approved Answer

c ) For the schedule developed using Johnson's rule, the total length of time taken to complete the seven printing and binding jobs is 5

c) For the schedule developed using Johnson's rule, the total length of time taken to complete the seven printing and binding jobs is
56 hours (enter your response as a whole number).
Part 11
d) The idle time in the binding shop based on the sequence developed using Johnson's rule is
enter your response here hour(s)(enter your response as a whole number).

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Small Business Management Entrepreneurship and Beyond

Authors: Timothy s. Hatten

5th edition

538453141, 978-0538453141

More Books

Students also viewed these General Management questions

Question

Why do I (you) believe that?

Answered: 1 week ago