C Homework Saved Help On June 15, 2021, Sanderson entered into a long-term construction contract to build a baseball stadium in Washington, D.C.for $320 milion. The expo completion date is April 1, 2023, just in time for the 2023 baseball season. Costs incurred and estimated costs to complete at year-end for the life of the contract are as follows ($ in millions): Costo incurred during the year Estimated cost to complete an of December 31 2021 2022 2023 $ 80 $40 $90 120 BO Required: 1. Compute the revenue and gross profit will Sanderson report in its 2021, 2022 and 2023 income statements related to this contract assuming Sanderson recognizes revenue over time according to percentage of completion. 2. Compute the revenue and gross profit will Sanderson report in its 2021 2022 and 2023 income statements related to this contract assuming this project does not qualify for revenue recognition over time. 3. Suppose the estimated costs to complete at the end of 2022 are $120 million instead of $80 million. Compute the amount of revenue and gross profit or loss to be recognized in 2022 assuming Sanderson recognizes revenue over time according to percentage of completion Complete this question by entering your answers in the tabs below. Saved Helg Required 1 Required 2 Required 3 Compute the revenue and gross profit will Sanderson report in its 2021, 2022, and 2023 income statements related to this contract assuming Sanderson recognizes revenue over time according to percentage of completion. (Enter your answers in millions. Loss amounts should be indicated with a minus sign. Use percentages as calculated and rounded in the table below to arrive at your final answer.) Percentages of completion Choose numerator Choose denominator % complete to date 2021 2022 0 0 2023 0 2021 Recognized in prior years To date Recognized in 2021 $ 0 Construction revenue Construction expense Gross profit (loss) 0 $ $ 0 2022 Recognized in prior years To date Recognized in 2022 0 Construction revenue Construction expense Gross profit (05) $ $ $ O 2023 Recognized in prior years To date Recognized in 2023 0 S $ 0 Construction revenue Construction expenso Gross profit (loss) $ 0 ording to percentage of completion. 2. Compute the revenue and gross profit will Sanderson report in its 2021, 2022, and 2023 income statements related to t assuming this project does not qualify for revenue recognition over time. 3. Suppose the estimated costs to complete at the end of 2022 are $120 million instead of $80 million. Compute the amour revenue and gross profit or loss to be recognized in 2022 assuming Sanderson recognizes revenue over time according to percentage of completion. Complete this question by entering your answers in the tabs below. Required 1 Required 2 Required 3 Compute the revenue and gross profit will Sanderson report in its 2021, 2022, and 2023 income statements related to this contract assuming this project does not qualify for revenue recognition over time. (Enter your answers in millions. Loss amounts should be indicated with a minus sign.) Year 2021 2022 2023 Revenue recognized million million million Gross Profit (Loss) recognized million million million Next > MacBook Pro