C. Mirza Water Assembly Plant wants to know the labor cost variance incurred in their Production. Below is the data related to material variance calculation.
C. Mirza Water Assembly Plant wants to know the labor cost variance incurred in their Production. Below is the data related to material variance calculation. 1. Standard Labor Cost per Hour: RM120 2. Actual Labor Cost per Hour: RM140 3. Standard Hours of Labor Worked: 2000 hours 4. Actual Hours of Labor Worked: 1800 hours Required: i. Labor Rate Variance (4 marks) ii. Labor Efficiency Variance (4 marks) Total Labor Cost Variance (4 marks)