CAC = $10 CPI = 1.16 TBC = $20 CEV = $12 If the work to be performed on the remaining portion of the project
CAC = $10 CPI = 1.16 TBC = $20 CEV = $12 If the work to be performed on the remaining portion of the project is done in line with the budget, regardless of the efficiency rate the project has had up to that point, what is the forecasted cost at completion