Calculate and prepare the static budget, flexible budget, and actual results based upon the following information: Budget Actual Volume Assumptions FFS Visit Volume 50,000 visits
- Calculate and prepare the static budget, flexible budget, and actual results based upon the following information:
Budget | Actual | |
Volume Assumptions | ||
FFS Visit Volume | 50,000 visits | 72,000 visits |
Payer Mix: | ||
Blue Cross | 30% | 30% |
Highmark | 70% | 70% |
Reimbursement Rates: | ||
Blue Cross | $45 per visit | $38 per visit |
Highmark | $40 per visit | $48 per visit |
Variable Costs | ||
Resource Inputs: | ||
Labor | 28,000 total hours | 40,000 total hours |
Supplies | 80,000 total units | 120,000 total units |
Resource Input Prices: | $35.00 per hour | $38.00 per hour |
Labor | ||
Supplies | $2,50 per unit | $3.50 per unit |
Fixed Costs | $500,000 | $500,000 |
- what are the profit variance, revenue variance, and cost variance?
- Considering the revenue side, what is the volume variance and price variance?
- Considering the cost side, what is the volume variance and management variance?
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started