Question

1 Approved Answer

Calculate and prepare the static budget, flexible budget, and actual results based upon the following information: Budget Actual Volume Assumptions FFS Visit Volume 50,000 visits

  1. Calculate and prepare the static budget, flexible budget, and actual results based upon the following information:
Budget Actual
Volume Assumptions
FFS Visit Volume 50,000 visits 72,000 visits
Payer Mix:
Blue Cross 30% 30%
Highmark 70% 70%
Reimbursement Rates:
Blue Cross $45 per visit $38 per visit
Highmark $40 per visit $48 per visit
Variable Costs
Resource Inputs:
Labor 28,000 total hours 40,000 total hours
Supplies 80,000 total units 120,000 total units
Resource Input Prices: $35.00 per hour $38.00 per hour
Labor
Supplies $2,50 per unit $3.50 per unit
Fixed Costs $500,000 $500,000
  1. what are the profit variance, revenue variance, and cost variance?
  2. Considering the revenue side, what is the volume variance and price variance?
  3. Considering the cost side, what is the volume variance and management variance?
  4. Break the management variance into labor, supplies, and fixed cost variances.
  5. Break down the labor and supplies variances into rate/price and efficiency/usage components

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Advanced Modelling In Mathematical Finance

Authors: Jan Kallsen, Antonis Papapantoleon

1st Edition

3319458736, 978-3319458731

More Books

Students also viewed these Finance questions

Question

Persuasive Speaking Organizing Patterns in Persuasive Speaking?

Answered: 1 week ago