Question
Calculate early start schedule, late finish, late start and slack Identify critical path(s). Where does the assumption of certainty enter into this model? What is
Calculate early start schedule, late finish, late start and slack
Identify critical path(s).
Where does the assumption of certainty enter into this model? What is the impact of elements being variable?
Activity | Duration | Predecessors |
1 Select vendor | 1 week | None |
2 Hire Finance module consultant | 4 weeks | 1 |
3 Hire Materials Mgmt consultant | 4 weeks | 1 |
4 Develop internal team | 10 weeks | None |
5 Select hardware system | 3 weeks | 2,3 |
6 Implement hardware system | 8 weeks | 5 |
7 Develop Finance interfaces | 8 weeks | 6 |
8 Install Finance module | 3 weeks | 6 |
9 Test Finance module | 2 weeks | 7,8 |
10 Put Finance module on-line | 0 | 9 |
11 Develop Materials Mgmt interfaces | 15 weeks | 6 |
12 Install Materials Mgmt module | 6 weeks | 10,11 |
13 Test Materials Mgmt module | 3 weeks | 12 |
14 Put Materials Mgmt module on-line | 0 | 13 |
15 Develop Finance user training | 5 weeks | 4,7 |
16 Develop Materials Mgmt user training | 7 weeks | 4,11 |
Please show formulas so that I can learn how to calculate LS and slack.
Step by Step Solution
3.47 Rating (160 Votes )
There are 3 Steps involved in it
Step: 1
Answer Solution Given Activity Duration Predecessors 1 Select vendor 1 week None ...Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started