Calculate the cost of each of these plans: Plan 1: Producing the monthly needs by varying the number of operators. The computing of the variation
Calculate the cost of each of these plans:
Plan 1:
Producing the monthly needs by varying the number of operators. The computing of the variation of the workforce is done according to the preceding month.
Plan 2:
Producing average monthly forecast demand over the six months by varying the workforce only the first month and maintaining the constant workforce after.
Plan 3:
Producing the lowest monthly forecast demand (April) by varying the effective the first month and
maintaining the constant workforce after. The company uses subcontractors for unmet needs through domestic production. Even, in case of subcontracting, the company C&C supports the storage costs and the materials costs.
The sales forecast for January to June are as follows (in units): 1800, 1500, 1100, 900, 1100,
and 1700.
The initial stock in early January and that of June were 400 units. The company has no
obligation to maintain stocks in other months. The initial workforce is 42 operators. Company
policy prohibits overtime; and the calculations should be made on the basis of 8 working
hours per day, 20 days a month.
The following cost elements were identified in the company's accounts:
Materials cost.......................................... 100 / unit
Inventory holding cost..........10 / unit-month
Shortage cost................. 50 / unit-month
Subcontracting cost................ 100 / unit (excluding material)
Hiring and training costs ... 1,000 / hiring
Lay-off cost...................... 2,000 / dismissal
Working time per unit............5 hours
Labor cost................ 15 / hour
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started