Given the following product structure, BOM, MPS and inventory status, develop MRP tables for all items using

Question:

Given the following product structure, BOM, MPS and inventory status, develop MRP tables for all items using EOQ method.image text in transcribed

Item Number of Units Required Initial Stock on Hand Lead Time Cc (Z)
Co (Z)
A 1 125 1 5 1000 B 1 20 2 6 1500 C 1 30 1 4 1800 D 1 50 1 3 1300 E 1 100 1 8 2000 Master Production Schedule Month 1 2 3 4 5 6 Projected Requirement — 100 — 80 150 200.AppendixLO1