Calculate the Critical Path and duration : Activity Predecessors Duration A - 7 B A 6 C A 5 D B 4 E C 9

Calculate the Critical Path and duration :

Activity Predecessors Duration
A - 7
B A 6
C A 5
D B 4
E C 9
F D 5
G E, F 10
H G 12