Question

1 Approved Answer

Calculate the ES, EF, LS, and LF times and the slack for each activity. Identify the critical path for the project. Can the project be

  1. Calculate the ES, EF, LS, and LF times and the slack for each activity.
  2. Identify the critical path for the project. Can the project be completed in 30 weeks?
  3. Assume that "Systems Analysis" actually finished at 8 weeks, "Design Input & Output" actually finished at 15 weeks, and "Design Database" actually finished at 19 weeks. Recalculate the expected project completion time. Which activities would you focus on to get the project back on schedule?

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Business and Administrative Communication

Authors: Kitty o. locker, Donna s. kienzler

10th edition

77830105, 978-0077830106, 978-0073403182

More Books

Students also viewed these General Management questions

Question

What are the relevant trends to consider?P-968

Answered: 1 week ago